          Logistics
        
        
          theMellrichstadt center
        
        
          will beoperational in2015
        
        
          the success of clipped activities in Germany has
        
        
          necessitated the construction of a new, modern
        
        
          logistics center, fitted with a sprinkler system. This
        
        
          will protect the parts stored there against the risk
        
        
          of fire. The commissioningof thisnew facility,which
        
        
          will improveworkingconditionsaswellastheservice
        
        
          provided tocustomers, isscheduled forApril2015.
        
        
          Specializationof fourEuropean
        
        
          fasteners sites
        
        
          Initiated in 2010, LISI AUTOMOTIVE’s European
        
        
          specializationprogram for fastenersplantswas fully
        
        
          completed in2014. It involvedthemodernizationand
        
        
          restructuring of the Business Group’s four plants:
        
        
          Delle and Saint-Florent in France, Fuenlabrada in
        
        
          Spain, and Kierspe in Germany. The first results
        
        
          producedby thisspecializationareexpected in2015.
        
        
          Dasle
        
        
          Extraordinary
        
        
          constructionwork
        
        
          The reconstruction of over 50% of the Dasle site in Franche-
        
        
          Comté was achieved without production loss. A remarkable
        
        
          organizational achievement. The site, transformed intoamodern
        
        
          and extremely functional plant, had to be totally redesigned to
        
        
          optimizeand rationalize itsentireworkflow.Thesecolossalworks,
        
        
          started in October 2012, increased the level of production by
        
        
          30%. Spread overmore than two years, they were completed in
        
        
          May 2015, without business interruption thanks to the seamless
        
        
          orchestrationofequipment relocation.
        
        
          A divisional plant performance booster, the
        
        
          operational excellence program, LISI Excellence
        
        
          AchievementProgram (LEAP),hasbeendeployed
        
        
          across all LISI AUTOMOTIVE plants in France
        
        
          and throughout the world. Four of these plants
        
        
          were rewarded in 2014 for the quality of such
        
        
          deployment: Beijing in China, Cejc in the Czech
        
        
          Republic, Fuenlabrada in Spain, and Melisey
        
        
          in France, demonstrating that LEAP knows no
        
        
          frontiers.